Building More Mini-dairy Processing Plants Ordered
By Kimeng Hilton, Cameroon Tribune, 29-05-2014
“The Prime Minister, Head of Government, Mr. Philemon YANG,
on Wednesday, 28 May 2014 as from 10:00 a.m. in the main building of
his Office, chaired an important Cabinet Meeting. In attendance were the
Vice-Prime Minister, Ministers of State, Ministers, Ministers-Delegate
and Secretaries of State.
Two statements featured on the agenda, namely:
- A statement by the Minister for Water Resources and Energy on: “Assessment of the implementation of the Lom Pangar Hydro Development Project;
- A statement by the Minister for Livestock, Fisheries and Animal Industries on: “The implementation progress of Cameroon’s Dairy Sub-Sector Development Programme”;
The Minister in charge of energy revealed that the construction of
the Lom Pangar dam, whose foundation stone was laid by the Head of State
on 3 August 2012, is advancing satisfactorily, as was observed during
the field visit on 24 May 2014. This CFAF 240.8 billion project, along
with dams being constructed at Memve’ele and Mekin and those planned on
River Bini at Warak and on River Menchum, is key to strengthening
Cameroon’s hydro capacities. Globally, the main objective of this
project is to reduce the seasonal variations of the flow of River
Sanaga, by regulating it and increase flow from 720 m3/s currently to 1,040 m3/s.
A key impact of the project will be higher output of the Song Loulou
and Edea plants of an additional 120 MW and the development of other
power plants downstream. Another expected impact is the substitution in
the East Region of cheaper hydro-electricity for more costly thermal
power currently being used, thanks to the construction of a 30-megawatts
plant at the toe of the dam and a 90-kilovolts power transmission line.
Implementation of the main project component, related to the dam, was
marked by the deviation of River Lom in July 2013. Works on the saddle
dam, the backfill dike and central gravity dam are advancing despite
some geotechnical problems.
The second project component – the plant at the foot of the dam and
the transmission line – is at the final phase of recruiting the
consulting engineer. When he assumes duty in the near future, work on
the final design of the plant at the foot of the dam, the transmission
line and the medium-voltage network will be expedited.
The project’s environmental and social component is also on track,
thanks to efficient waste management, the mitigation of social impacts
and the management of the Deng-Deng forest.
Although all families affected by the project have been compensated,
complaints continue to be received. The plan to resettle some families
on the chosen relocation sites has almost been fully executed.
On 31 March 2014, the financial execution of the project was around
CFAF 50.7 billion against an expected CFAF 240.8 billion, corresponding
to an overall implementation rate of 21.1%.
The Minister for Water Resources and Energy expressed optimism about
meeting the objective of first priming in the last quarter 2015 and
commissioning the plant in 2018.
After noting this appraisal report and expressing Government’s
satisfaction with the conduct of the project, the Prime Minister
prescribed various measures aimed at expediting the construction of the
Lom Pangar dam, including the rapid removal of timber in the holding
ground, at the suite of the Minister for Forestry and Wildlife.
Cabinet Meeting proceedings continued with the statement by the
Minister in charge of livestock on the implementation progress of
Cameroon’s Dairy Sub-sector Development Programme. It revealed that
Cameroon’s dairy sub-sector, based on the processing of cow-milk,
produces about 184,000 tons of milk/year, from a cattle inventory of
close to 6 million animals reared in all regions.
This Dairy Sub-Sector Development Programme, costing over CFAF 19
billion, seeks to channel and revitalize this production to meet
consumption of dairy products estimated at 269,000 tons in 2015 and
310,000 tons in 2025. The expected benefits are mainly enhanced food and
nutritional security, lower imports, amounting to CFAF 28 billion in
2013 and job creation through a better structuring of the sub-sector.
Actions undertaken include, inter alia: the construction of 7
collection centres with total capacity of 20,000 litres/day; the
construction of 4 mini-processing plants of total capacity of 10,000
litres/day in Meiganga, N'Gaoundéré, Garoua and Maroua; and the ongoing
construction of 3 mini-processing plants in Mbengwi in Momo Division,
Bot in Donga Mantung Division and Esu in Menchum Division.
Concurrently, the State is in the process of launching the Ngaoundere
Dairy Project that will be ceded to a private operator after
consideration of nine proposals selected after a call for expression of
interest.
The Minister pointed out that prospects in the dairy sub-sector are
bright, considering the existing potential. However, efforts are needed
to update the legal framework, constitute a herd commensurate with
substantial output as well as structure and train stakeholders.
After the ensuing discussions, the Head of Government asked the
Minister for Livestock, Fisheries and Animal Industries to continue the
extension of the project to build mini-dairy processing plants in all
cattle-rearing regions and, in collaboration with the Minister for
Finance, speed up the revitalization of activities of the Ngaoundere
Dairy Project.
The Cabinet Meeting was adjourned at 12:30 p.m.”
Prime Minister Yang chairing the cabinet meeting.
Commentaires
Enregistrer un commentaire